The amendment regulates earthquake maximum alerts, maximum alerts for other phenomena and Civil Protection preventive messages. Reception of these three categories cannot be disabled by users.
It provides display, sound, vibration and testing requirements. Existing accredited and authorised bodies and laboratories have 60 calendar days from publication to update their accreditation and authorisation.
Separate transitional rules apply to existing certificates.
Impact
Impact assessment: High.
Key reasons: The amendment becomes effective on 27 October 2026, calculated under Transitional Article One, and changes CBS alert functionality and verification requirements. Assessment also depends on the laboratory and certification-body authorisations addressed in Transitional Articles Two-Four.
Who is affected?
Manufacturers and certificate holders for covered mobile terminals, certification bodies, test laboratories, and teams responsible for terminal software, alert interfaces, acoustic and vibration behaviour, testing and certification records.
Conclusion:
Review each model and certificate against the applicable transition. Under Article Six, capable equipment may follow the operating-system update route, with notice and subsequent surveillance when that route is chosen. Article Seven requires notice of inability for incapable equipment and excludes extensions and surveillance in that case. Article Eight avoids recertification or re-homologation for those specified cases; Article Five preserves previously filed homologation applications. Document the applicable route and confirm authorised assessment availability. The high-priority rating and recommended model review are internal editorial assessments.
Regulatory Authority
Comisión Reguladora de Telecomunicaciones (CRT)
Regulatory Impact
| Impact Type | Status |
|---|---|
| Top Priority | |
| Type Certificate | |
| Spectrum Bands | |
| Import Changes (HS Codes) | |
| Standard Changes | |
| Product Changes | |